Capital Budget - Public Works- Project Highlights

Public Works Capital Projects

Project Highlights

2004 Status Report

Projects Budget Comments
Traffic Signal Modification - ADA $200,000 Projects in construction phase
TDOT State Route Paving Program 2,000,000 Projects are complete except for punch list items. Once punch list is complete, projects will be close out. Remaining funds will be used for future 20% SR SW paving projects which are in design phase
Bridge Program - Maintenance, Repair and Rehabilitation 4,800,000 Funds allocated for 73 rehabilitations or replacements. Remaining projects in construction phase.
Demonbreun Bridge - Improvements 238,000 Project in closeout phase. Remaining funds allocated for Environmental Study on Shelby -Demonbreun
Roadway Maintenance 9,200,000 All Projects are closed out.
Sidewalks - Construct / Improve 3,750,000 Projects in construction.
Bridge Replacements 770,000 Funds will be used for replacement of 3 bridges. Engineering is underway. Projects in design/development phase.
Old Landfill Remediation / Closure 900,000 Closure of Ash monofill in final stages. Remaining funds are needed to ensure that any significant costs that are identified during TDEC/PW inspections will be available for immediate site corrections to remain in compliance.
Recycling Roll Offs 100,000 Roll offs for materials recycled at Recycling & Convenience centers - 40 containers.
Public Works - Various Equipment 477,500 Project is complete.
Public Works Facilities 150,000 Project is complete.

2005 Status Report

Projects Budget Comments
Bridge Program – Maintenance , Repair And Rehabilitation $3,000,000 Projects in planning and construction phase
Roadway Improvements In G.S.D. 20,000,000 Projects in development, design, and right-of-way phases.
Bridges Drainage - Replacement/Repairs 500,000 Projects are complete.
Bike Route Strategic Plan 600,000 Projects in design phase.
Demonbreun Bridge - Improvements 1,660,000 Project is in close out with State . Any remaining funds will be applied to completion Demonbreun Street corridor.
Parking Garage Equipment – Courthouse 462,000 Working with Purchasing and Downtown Partnership
Replacement Of Safety Lighting On Selected Downtown Corridors 1,000,000 West End Ave Construction early 2008
Roadway Maintenance In GSD 5,900,000 Group paving projects are complete. Consultant projects underway are being closed out. Remaining funds are planned to be used on future consultant contracts
Roadway Maintenance In USD 4,800,000 Group paving projects are complete. Consultant projects underway are being closed out. Remaining funds are planned to be used on future consultant contracts
Sidewalks -Construct/ Improve In GSD 2,000,000 Remaining projects in design and construction phases.
TDOT State Route Paving Program - Ramps – GSD 1,500,000 Projects are completed except for punch list items. Once punch list is complete, projects will be closed out. Remaining funds will be used for future 20% SR SW paving projects which are in design phase
Traffic Signal Modification-ADA-GSD 250,000 Part of overall Signal Plan.
Sidewalks - Construct/Improve In USD 6,000,000 Remaining projects in design and construction phases.
TDOT State Route Paving Program - Ramps – USD 500,000 Projects are completed except for punch list items. Once punch list is complete, projects will be closed out. Remaining funds will be used for future 20% SR SW paving projects which are in design phase
Traffic Signal Equipment - Modify 3,930,000 Part of overall Signal Plan
Traffic Signal Modification-ADA-USD 750,000 Part of overall Signal Plan
Woodland Street Bridge Over Cumberland River 3,550,000 Project in close out phase.
Bordeaux Landfill Cap Remediation Pre -1990 Areas 4,200,000 Project is complete. In post-closure maintenance phase. Encumbrance overage will be corrected.

2006 Status Report

Projects Budget Comments
Traffic Signal Modification - ADA - GSD $250,000 ADA improvements to Signal Plan.
TDOT State Route Paving Program - Ramps - GSD 1,500,000 Projects are planned for construction
Bridge Program - Maintenance , Repair And Rehabilitation 6,500,000 Projects are in planning or construction phases.
Bridges Drainage - Replacement/Repairs 500,000 Projects are in planning phase.
Roadway Improvements 20,000,000 Projects are in survey, preliminary engineering, and design phase.
Paving Program In GSD 7,645,000 Projects are in the contract, bid, or construction phase.
Sidewalks -Construct And Improve In GSD 4,000,000 Projects in construction phase
Bike Route Strategic Plan 600,000 Projects in design phase.
Traffic Signal Modification - ADA - USD 1,000,000 Part of overall Signal Growth Plan.
TDOT State Route Paving Program - Ramps - USD 500,000 Projects are in design phase.
Paving Program In USD 6,255,000 Projects are in the contract, bid, or construction phase.
Sidewalks - Construct / Improve In USD 6,000,000 Projects in construction phase. Scheduled for Jan. 08
Traffic Signal Equipment - Modify 4,100,000 Part of overall Signal Growth Plan.
Replacement Of Safety Lighting On Selected Downtown Corridors 2,000,000 Design complete-construction in early 2008
Bordeaux Landfill - Repairs / Updates - Including Gas Collection System 1,300,000

Funds needed to ensure that any significant costs that are identified during TDEC/PW inspections will be available for immediate site corrections to remain in compliance with state and federal regulations

2007 Status Report

Projects Budget Comments
Bridge Program - Maintenance , Repair And Rehabilitation $1,675,000 Projects are in design and construction phase
Bridges Drainage - Replacement/Repairs 565,000 Projects are in design and construction phase
Roadway Improvements In GSD. 10,000,000 Projects are in preliminary design phase
Bike Route Strategic Plan 300,000 Projects in design
Bordeaux Landfill 2,800,000 Any post closure funds needed for Bordeaux should be covered in 07PW00005. It is not recommended at this time that a perimeter gas collection system be installed
Paving Program In GSD 4,592,500 Projects are in design phase
Sidewalks -Construct And Improve In GSD 1,000,000 Projects are scheduled for construction to start in Jan. 08
TDOT State Route Paving Program - Ramps – GSD 1,000,000 Projects are in design phase
Traffic Signal Modification - ADA – GSD 125,000 Projects are in design phase
Traffic Signal Modification - USD – ADA 500,000 Projects are in design phase
TDOT State Route Paving Program - Ramps – USD 500,000 Projects are in design phase
Paving Program In USD 3,757,500 Projects are in design phase
Sidewalks - Construct/Improve In USD 4,000,000 Projects are scheduled for construction to start in Jan. 08
Traffic Signal Equipment – Modify 2,170,000 Projects are in design phase
Replacement Of Safety Lighting On Selected Downtown Corridors 1,000,000 Design complete-construction in early 2008
Bridge Replacements 300,000 projects are in design and construction phase
Annexation In District 32 2,000,000 Project is complete.
District 32 - Refinancing Of Debt To NES 10,500,000 In Process