We appreciate your patience as we perform regular maintenance and repair to our infrastructure.
Sincerely,
Scott Potter, Director
12th Ave South Water Main Replacement Phases 4 - 6
- Project Number: 18WC0092
- Project Summary: The project consists of the construction and installation of approximately 129 linear feet of 4-inch water main (DIP), 1,398 linear feet of 6-inch water main (DIP), 26,225 linear feet of 8-inch water main (DIP), 3,380 linear feet of 12-inch water main (DIP), 921 linear feet of 16-inch water main (DIP), 1,461 linear feet of 24-inch water main (DIP), and 71 fire hydrant assemblies within the roadway.
- Council District(s): 17 - Colby Sledge and 18 - Tom Cash
- Contractor: JSJ Construction
- Project Timeline: April 2023 - Spring 2025
- Work Hours: Daytime work hours to be determined by NDOT
- Road Closure/Detour: Rolling lane closures along throughout project construction.
- Service Interruptions: Unexpected service interruptions are not anticipated, and customers will be notified, in advance, of any planned interruptions which will be of short duration.
- 12th Ave. S. Water Main Replacement Vicinity Map
This project will be divided into five (5) segments. Work in segment 1 is complete; Segment 2 is nearing completion and crews are working in Segment 3.
- 12th Ave South Segment 1 Map
- 12th Ave South Segment 2 Map
- 12th Ave South Segment 3 Map
- 12th Ave South Segment 4 Map
- 12th Ave South Segment 5 Map
38th Avenue Water Storage Tank
- Project Number: 16WC0018
- Project Summary: The project is located between 38th Ave N. and 37th Ave. N. The project consists of the demolition of the existing water storage tank and the construction of a new 2.5 million gallon above ground water storage tank. Construction also includes almost 1,000 linear feet of 12” and 24” water main, a new fire hydrant, and 679 linear feet of stormwater infrastructure. Other miscellaneous site improvements such as a sidewalk and fencing are included in the project scope. Our contractor will attempt to minimize disruption to the community as much as possible. However, nearby residents will see an increase in truck traffic and may experience noise and dust associated with demolition and construction. Customers will be notified prior to any scheduled service interruption 24 hours in advance either in person or with a door hanger. Once the project is complete, the community will have new water reservoir providing improved water quality, reduced risk of pressure surges (reduced potential for line breaks and water loss), and additional emergency storage.
A community meeting will be held 6:30 p.m.-8:00 p.m. on Thursday, February 29, 2024, at the McCabe Community Center, 101 46th Avenue N., Nashville, TN 37209.
- Council District: 24 – Brenda Gadd
- Contractor: Blakely Construction Services. LLC
- Project Timeline: March 2024 - September 2025
- Work Hours: Daytime work hours typical, ROW improvement construction work hours to be determined by NDOT. Infrastructure connections in Charlotte Ave. (SR24) required to be done at night per TDOT.
- Road Closure/Detour: Rolling lane closures
- Project Contact: Jeff Duncan – Metro Water Services 615-862-4959, [email protected]
- 38th Ave Water Storage Tank Project Vicinity Sketch
Drummond Drive Water and Stormwater Improvement Project
- Project Numbers: 22WG0023, 23SC0146, and 23SWC011
- Project Summary: The project consists of the replacement of existing 4-inch and 6-inch water mains with approximately 6,800 linear feet of 8-inch water main. The project is located on Glenrose Ave/Drummond Dr and Wildview Dr, beginning near the Glenrose Interstate 24 underpass, crossing the Thompson Ln intersection, and ending at the intersection of Crowder Ct. The new water main will improve water quality and fire flow . Additionally, a failed corrugated metal stormwater culvert beneath the roadway at 924 Drummond Dr will be replaced, improving drainage to Mill Creek. The work will be constructed in segments with pavement restoration and site cleanup to be completed before beginning the next segment. Disruptions to water service, when required, will be short in duration and coordinated in advance to minimize the impact to residents (typically performed at night). Noise, dust, and truck traffic disturbances created by construction activities will be isolated to localized areas of excavation as the project progresses. Upon project completion, the roadway will receive full width repaving. A portion of this job overlaps with NDOT’s larger paving project that will resurface E Thompson Ln.
- Council District: 16 – Ginny Welsch
- Contractor: Walker Building Group
- Project Timeline: April 2024 - March 2025
- Work Hours: Hours to be determined by NDOT; Daylight hours anticipated, possible night work crossing the E Thompson intersection.
- Road Closure/Detour: Water main construction will occur within the roadway. A minimum of one lane will remain open to traffic. A roadway detour via Wildview Dr will be provided during the stormwater culvert replacement near 924 Drummond Dr.
- Project Contact: Rick Fussell – Metro Water Services, 615-405-8723, [email protected]
- Drummond Dr. Improvements Project Vicinity Map
East Nashville Water Main Replacement - Phase 1
A community meeting will be held at 6 p.m. on April 9, 2024, at the McFerrin Community Center.
- Project Number: 21WC0106
- Project Summary: The project will replace approximately 18,000 linear feet (LF) of various-sized existing water mains (2.25-inch through 12-inch cast iron pipes) with new ductile iron pipe water mains (6-inch through 12-inch). The existing water mains are undersized, very old, made of outdated pipe material, and have breakage histories. Phase One is bounded by Joseph Avenue, Cleveland Street, Lischey Avenue, and Meridian Street near Dickerson Pike. Water main construction will not take place in Cleveland Street or Lischey Avenue during Phase One. The project will increase water services and reliability and provide improved fire protection. MWS personnel and their contractor will work to minimize construction concerns such as noise, dust, and truck traffic. Service interruptions will be minimal and will be scheduled with impacted residents ahead of time.
- Council District: 5 – Sean Parker
- Contractor: JSJ Construction, LLC
- Project Timeline: Spring 2024 - Summer 2025 (Phase 1)
- Work Hours: 7 a.m. - 5 p.m. Monday-Friday
- Road Closure/Detour: Moving closures will be necessary; however, one lane will remain open at all times.
- Project Contact: Justin Pendley – Metro Water Services 615-775-3655 [email protected]
- Phase 1 - East Nashville Water Main Replacement Vicinity Map
Flowmeters Phase 1
- Project Number: 24WG0008
- Project Summary: The project will help to reduce water loss within our system by installing flowmeters throughout the Metropolitan area - most near existing Pressure Reducing Valve (PRV) locations.
- Council District: 12 – Erin Evans, 6 – Clay Capp, 26 – Courtney Johnston, 27 – Bob Nash, 31 – John Rutherford, and 33 – Antoinette Lee
- Contractor: Garney Construction
- Project Timeline: Date of start varies based on which flowmeter location is under construction (see pdf of map and/or list below)
- Site 1 – Roxborough (9/16/2024)
- Site 8 – Airport (9/23/24)
- Site 10 – Mill Run (9/30/24)
- Site 3 – Shelby Park (10/7/24)
- Site 12 – Pettus Rd Altitude Valve (10/14/24)
- Site 4 – Brentwood Highlands (10/21/24)
- Site 5 – Ocala (10/28/24)
- Site 11 – Pettus Rd at S. OHB (11/4/24)
- Work Hours: 9 a.m.-3 p.m. Monday-Friday
- Road Closure/Detour: Most of the flowmeter vaults will be located within ROW out of the traffic area; however, in some instances there may be moving closures along streets during installation. One lane will remain open at all times. All TDOT and NDOT requirements shall be followed.
- Project Contact: Justin Pendley – Metro Water Services 615-775-3655 [email protected]
- Flowmeter Phase 1 Project Vicinity Sketch
Main Street - Gallatin Road Water Main Improvements
- Project Number: 22WG0024
- Project Summary: Installation of approximately 7,080 linear feet (LF) of 12-inch water main (Ductile Iron Pipe) from South 5th to West Eastland along Main Street – Gallatin Rd.
- Council District(s): 5 - Sean Parker and 6 - Clay Capp
- Contractor: Garney Companies, Inc.
- Project Timeline: January 2024 - January 2025
- Work Hours: To be determined by NDOT.
- Road Closure/Detour: Moving closures - One lane will remain open at all times.
- Project Contact: Justin Pendley – Metro Water Services 615-775-3655, [email protected]
- Main Street-Gallatin Road Water Main Improvement Vicinity Map
Whittemore Lane Water Main Replacement
- Project Number: 19WG0064
- Project Summary: The project is located on Whittemore Lane between Old Hickory Blvd. and Burkitt Road. The project consists of the installation of approximately 3680 linear feet of 12-inch water main (DIP), 85 linear feet of 6-inch water main (DIP), one flowmeter, and 6 fire hydrant assemblies with associated fittings within the roadway
Our contractor will attempt to minimize disruption to the community as much as possible. However, nearby residents will see an increase in truck traffic and may experience noise and dust associated with trenching of the roadway for the new water main. Customers will be notified in person or by doorhanger 24 hours prior to scheduled service interruptions, necessary to be connected to the new main.
- Council District: 31 - John Rutherford and 33 - Antoinette Lee
- Contractor: JSJ Construction, LLC
- Project Timeline: November 2024 - May 2025
- Work hours: Daytime
- Road Closure/Detour: Rolling lane closures during the day - one lane will remain open at all times. Open trenches will be plated at night.
- Project Contact: Justin Pendley – Metro Water Services 615-775-3655 [email protected]
- Whittemore Lane Water Main Replacement Vicinity Map
Contact Information
If you have questions or concerns regarding a Metro Water Services project, please call 615-862-4555.
In case of a water, sewer or stormwater emergency, please call 615-862-4600.
Process Advancements
Metro Water Services (MWS) has always delivered safe, clean, and reliable water to our customers and we strive to stay informed of new technologies and ahead of new regulations. The Process Advancements Project will allow MWS to proactively address aging infrastructure, expand capacity, reduce flood risk, and incorporate the use of new treatment technologies for enhanced water quality at our water treatment facilities, preparing them for the next generation.
Join us for a community meeting regarding the Omohundro Process Advancements:
- Date: Monday, April 22, 2024
- Time: 6:00 p.m.
- Location: Shelby Bottoms Nature Center - 1900 Davidson Street, Nashville, TN 37206
Learn more about how we are Advancing MWS Water
Clean Water Nashville
Clean Water Nashville Overflow Abatement Program Projects List
The Clean Water Nashville Overflow Abatement Program is an initiative led by Metro Water Services (MWS) in coordination with partner agencies including the U.S. Environmental Protection Agency (EPA) and the Tennessee Department of Environment and Conservation (TDEC) for the purpose of meeting the Clean Water Act requirements and, in the process, ensuring the environmental health of the Cumberland River and its tributaries for future generations.
NashDigs
NashDigs is a web-based map viewer that provides users with online public access to information on active infrastructure construction projects in and around Nashville, including Metro Water Services water, sewer, and stormwater projects.
Projects Not Listed
For information on a construction project that is not listed on this page, please contact Customer Service at 615-862-4600.