To maintain the high level of service our community expects, it is often necessary to replace or rehabilitate infrastructure.
In each of our projects, we strive to minimize disruption to the community as much as possible. However, during infrastructure projects, residents will see an increase in truck traffic and may experience noise and dust associated with construction.
If a scheduled service interruption is necessary as part of a project listed below, customers will be notified 24 hours in advance either in person or with a door hanger.
Upon project completion, final paving of damaged roadways will be done after a settling period.
Our goal is to complete projects as quickly as possible, but MWS will not compromise the safety of residents or workers. Construction delays may occur due to weather or other safety concerns.
We appreciate your patience.
Sincerely,
Scott Potter, Director
38th Avenue Water Storage Tank
- Project Number: 16WC0018
- Project Summary: The project is located between 38th Ave N. and 37th Ave. N. The project consists of the demolition of the existing water storage tank and the construction of a new 2.5 million gallon above ground water storage tank. Construction also includes almost 1,000 linear feet of 12” and 24” water main, a new fire hydrant, and 679 linear feet of stormwater infrastructure. Other miscellaneous site improvements such as a sidewalk and fencing are included in the project scope. Our contractor will attempt to minimize disruption to the community as much as possible. However, nearby residents will see an increase in truck traffic and may experience noise and dust associated with demolition and construction. Customers will be notified prior to any scheduled service interruption 24 hours in advance either in person or with a door hanger. Once the project is complete, the community will have new water reservoir providing improved water quality, reduced risk of pressure surges (reduced potential for line breaks and water loss), and additional emergency storage.
A community meeting will be held 6:30 p.m.-8:00 p.m. on Thursday, February 29, 2024, at the McCabe Community Center, 101 46th Avenue N., Nashville, TN 37209.

- Council District: 24 – Brenda Gadd
- Contractor: Blakely Construction Services. LLC
- Project Timeline: March 2024 - September 2025
- Work Hours: Daytime work hours typical, ROW improvement construction work hours to be determined by NDOT. Infrastructure connections in Charlotte Ave. (SR24) required to be done at night per TDOT.
- Road Closure/Detour: Rolling lane closures
- Project Contact: Jeff Duncan – Metro Water Services 615-862-4959, jeff.duncan@nashville.gov
- 38th Ave Water Storage Tank Project Vicinity Sketch
Audubon Road Water Main Replacement
- Project Number: 24WG0001
- Project Summary: The project is located off of Audubon Rd. and Gray Oaks Dr. (see vicinity map below). The project includes the installation of approximately 1680 linear feet of new water main in various sizes, 2 fire hydrant assemblies with associated fittings, and abandonment old water mains.
MWS personnel and our contractor will attempt to minimize construction concerns and ensure site safety. However, nearby residents will see an increase in truck traffic and may experience noise and dust associated with construction activities. Customers will be notified in person or by doorhanger 24 hours prior to scheduled service interruptions, necessary to be connected to the new main.
- Council District: 25 – Jeff Preptit
- Contractor: Civil Constructors, LLC
- Project Timeline: January 2025 – August 2025
- Work hours: Daytime
- Road Closure/Detour: Connection in Audubon Rd. and Gray Oaks Dr. will require temporary lane closures. Traffic will be routed around work zone.
- Project Contact: Rick Fussell – Metro Water Services, 615-405-8723, rick.fussell@nashville.gov
- Audubon Road Water Main Replacement Vicinity Map
East Nashville Water Main Replacement - Phase 1
A community meeting will be held at 6 p.m. on April 9, 2024, at the McFerrin Community Center.
- Project Number: 21WC0106
- Project Summary: The project will replace approximately 18,000 linear feet (LF) of various-sized existing water mains (2.25-inch through 12-inch cast iron pipes) with new ductile iron pipe water mains (6-inch through 12-inch). The existing water mains are undersized, very old, made of outdated pipe material, and have breakage histories. Phase One is bounded by Joseph Avenue, Cleveland Street, Lischey Avenue, and Meridian Street near Dickerson Pike. Water main construction will not take place in Cleveland Street or Lischey Avenue during Phase One. The project will increase water services and reliability and provide improved fire protection. MWS personnel and their contractor will work to minimize construction concerns such as noise, dust, and truck traffic. Service interruptions will be minimal and will be scheduled with impacted residents ahead of time.
- Council District: 5 – Sean Parker
- Contractor: JSJ Construction, LLC
- Project Timeline: Spring 2024 - Summer 2025 (Phase 1)
- Work Hours: 7 a.m. - 5 p.m. Monday-Friday
- Road Closure/Detour: Moving closures will be necessary; however, one lane will remain open at all times.
- Project Contact: Justin Pendley – Metro Water Services 615-775-3655 justin.pendley@nashville.gov
- Phase 1 - East Nashville Water Main Replacement Vicinity Map
Flowmeters Phase 1
- Project Number: 24WG0008
- Project Summary: The project will help to reduce water loss within our system by installing flowmeters throughout the Metropolitan area - most near existing Pressure Reducing Valve (PRV) locations.
- Council District: 12 – Erin Evans, 6 – Clay Capp, 26 – Courtney Johnston, 27 – Bob Nash, 31 – John Rutherford, and 33 – Antoinette Lee
- Contractor: Garney Construction
- Project Timeline: Date of start varies based on which flowmeter location is under construction (see pdf of map and/or list below)
- Site 1 – Roxborough (9/16/2024)
- Site 8 – Airport (9/23/24)
- Site 10 – Mill Run (9/30/24)
- Site 3 – Shelby Park (10/7/24)
- Site 12 – Pettus Rd Altitude Valve (10/14/24)
- Site 4 – Brentwood Highlands (10/21/24)
- Site 5 – Ocala (10/28/24)
- Site 11 – Pettus Rd at S. OHB (11/4/24)
- Work Hours: 9 a.m.-3 p.m. Monday-Friday
- Road Closure/Detour: Most of the flowmeter vaults will be located within ROW out of the traffic area; however, in some instances there may be moving closures along streets during installation. One lane will remain open at all times. All TDOT and NDOT requirements shall be followed.
- Project Contact: Justin Pendley – Metro Water Services 615-775-3655 justin.pendley@nashville.gov
- Flowmeter Phase 1 Project Vicinity Sketch
Main Street - Gallatin Road Water Main Improvements
- Project Number: 22WG0024
- Project Summary: Installation of approximately 7,080 linear feet (LF) of 12-inch water main (Ductile Iron Pipe) from South 5th to West Eastland along Main Street – Gallatin Rd.
- Council District(s): 5 - Sean Parker and 6 - Clay Capp
- Contractor: Garney Companies, Inc.
- Project Timeline: January 2024 - January 2025
- Work Hours: To be determined by NDOT.
- Road Closure/Detour: Moving closures - One lane will remain open at all times.
- Project Contact: Justin Pendley – Metro Water Services 615-775-3655, justin.pendley@nashville.gov
- Main Street-Gallatin Road Water Main Improvement Vicinity Map
Straightway Circle Water Main Improvements
- Project Number: 23WG0087
- Project Summary: Installation of approximately 345 linear feet of 6-inch and 12-inch water main within Straightway Circle and Chapel Avenue, as well as a new fire hydrant. Existing private water service lines and water meters will be re-located in conjunction with this new water main. The goal of this project is to provide a better water service setup for properties along the Straightway Circle Right-of-Way, along with better fire protection. MWS and their contractor will work to minimize noise, dust, drainage, delays in public services (garbage pickup, mail delivery, etc.) or other impacts associated with construction and work with impacted properties to maintain property access as best as possible (by road plating, etc.). Scheduled water outages will be pre-arranged with impacted property owners. The road and right-of-way will be restored to pre-construction conditions, to the extent possible (road to be repaved upon project conclusion).
- Council District(s): 6 - Clay Capp
- Contractor: Civil Constructors, LLC
- Project Timeline: March 2025 - May 2025
- Work Hours: 7 am - 5 pm
- Road Closure/Detour: Moving closures - One lane will remain open at all times.
- Project Contact: Rick Fussell – Metro Water Services, 615-862-4555, rick.fussell@nashville.gov
- Straightway Circle Water Main Vicinity Map
Whittemore Lane Water Main Replacement
- Project Number: 19WG0064
- Project Summary: The project is located on Whittemore Lane between Old Hickory Blvd. and Burkitt Road. The project consists of the installation of approximately 3680 linear feet of 12-inch water main (DIP), 85 linear feet of 6-inch water main (DIP), one flowmeter, and 6 fire hydrant assemblies with associated fittings within the roadway
Our contractor will attempt to minimize disruption to the community as much as possible. However, nearby residents will see an increase in truck traffic and may experience noise and dust associated with trenching of the roadway for the new water main. Customers will be notified in person or by doorhanger 24 hours prior to scheduled service interruptions, necessary to be connected to the new main.
- Council District: 31 - John Rutherford and 33 - Antoinette Lee
- Contractor: JSJ Construction, LLC
- Project Timeline: November 2024 - May 2025
- Work hours: Daytime
- Road Closure/Detour: Rolling lane closures during the day - one lane will remain open at all times. Open trenches will be plated at night.
- Project Contact: Justin Pendley – Metro Water Services 615-775-3655 justin.pendley@nashville.gov
- Whittemore Lane Water Main Replacement Vicinity Map
Willshire Drive Water Main Replacement
- Project Number: 24WG0035
- Project Summary: The project is located in Willshire Drive starting at the intersection with Priest Road. The project consists of the installation of approximately 1081 linear feet of new 6-inch water main (DIP) and 1 fire hydrant assembly with associated fittings within the roadway and abandonment of old water main.
MWS personnel and our contractor will attempt to minimize construction concerns and ensure site safety. However, nearby residents will see an increase in truck traffic and may experience noise and dust associated with construction activities. Additionally, a portion of the ROW near the dead-end will be utilized to store construction materials. Customers will be notified in person or by doorhanger 24 hours prior to scheduled service interruptions, necessary to be connected to the new main.
- Council District: 34 - Sandy Ewing
- Contractor: Civil Constructors, LLC
- Project Timeline: January 2025 - April 2025
- Work hours: Daytime
- Road Closure/Detour: Connection in Priest Road and Willshire Drive will require temporary lane closure. Traffic will be routed around work zone.
- Project Contact: Rick Fussell – Metro Water Services, 615-405-8723, rick.fussell@nashville.gov
- Willshire Drive Water Main Replacement Vicinity Map
Contact Information
If you have questions or concerns regarding a Metro Water Services project, please call 615-862-4555.
In case of a water, sewer or stormwater emergency, please call 615-862-4600.
Process Advancements
Metro Water Services (MWS) has always delivered safe, clean, and reliable water to our customers and we strive to stay informed of new technologies and ahead of new regulations. The Process Advancements Project will allow MWS to proactively address aging infrastructure, expand capacity, reduce flood risk, and incorporate the use of new treatment technologies for enhanced water quality at our water treatment facilities, preparing them for the next generation.
Join us for a community meeting regarding the Omohundro Process Advancements:
- Date: Monday, April 22, 2024
- Time: 6:00 p.m.
- Location: Shelby Bottoms Nature Center - 1900 Davidson Street, Nashville, TN 37206
Learn more about how we are Advancing MWS Water
Clean Water Nashville
Clean Water Nashville Overflow Abatement Program Projects List
The Clean Water Nashville Overflow Abatement Program is an initiative led by Metro Water Services (MWS) in coordination with partner agencies including the U.S. Environmental Protection Agency (EPA) and the Tennessee Department of Environment and Conservation (TDEC) for the purpose of meeting the Clean Water Act requirements and, in the process, ensuring the environmental health of the Cumberland River and its tributaries for future generations.
NashDigs
NashDigs is a web-based map viewer that provides users with online public access to information on active infrastructure construction projects in and around Nashville, including Metro Water Services water, sewer, and stormwater projects.
Projects Not Listed
For information on a construction project that is not listed on this page, please contact Customer Service at 615-862-4600.