Project Description
This project will install pedestrian improvements along Gallatin Pike from Alta Loma Road to Liberty Lane. The project would curb and gutter, a 4’ grass strip, 14-foot shared-use path on both sides of Gallatin Pike, prepare sites for connection to future bus stops on the north/west side, improve signalized intersections with crosswalks and pedestrian countdown timers, make improvements to WeGo Transit bus stop locations on the south/east side of Gallatin Pike by adding a 14-foot shared-use path, and adding Americans with Disabilities Act (ADA) compliant upgrades where needed.
This project is federally funded, locally managed and is monitored by the TDOT Local Programs Development Office.
Project Funding: 80% Federal and 20% Local
- Length: 1.14 miles
- Cross-Section: 10-foot shared use path
- Estimated Project Cost: $7,060,000
Project Limits
Alta Loma to Liberty Lane (1.14 miles)
Council District 10: Council Member Jennifer Frensley Webb
Project Update: August 2024
Phase: Design
The National Environmental Policy Act (NEPA) re-evaluation is in progress. The project team met with Council Member Jennifer Frensley Webb to share proposed project layout and details last quarter. Reoccurring project meetings are ongoing with the project team and initial right-of-way (ROW) plans have been submitted and will be reviewed by the Nashville Department of Transportation and Multimodal Infrastructure (NDOT) staff.
Timeline
Note: Estimated timeline dates are subject-to-change based on most current projected schedules from multiple vendors and departments.
Project Development Schedule Milestones
- Preliminary Engineering: Completed 2017
- Environmental/NEPA: Completed 2019
- NEPA Re-Evaluation: August 2024
- Initial Utility Coordination: September 2024
- Design (Preliminary right-of-way plans development): August 2024
- Design (Final right-of-way plans development): September 2025
- Right-of-Way (ROW) Acquisition start: Spring 2025
- Final Utility Coordination: Fall/Winter 2026
- Final Construction Plans: Fall/Winter 2027
Construction Schedule Milestones
- Advertisement for Construction: January 2028
- Contract Award: March 2028
- Contract Fully Executed: Spring 2028
- Estimated Construction Start: Summer 2028
- Estimated Construction Completion: Summer 2029
For more information, please contact the Metro Project Manager at 901-497-8979.
Gallatin Pike looking north from Alta Loma (beginning of project)
Gallatin Pike at Liberty Lane (end of project)