Realignment of Crestmoor Road at Hillsboro Pike to align with Glen Echo Road. Project also includes a new water main within Hillsboro Pike.
Project Funding: 100% Local
Project Limits
Intersection of Crestmoor Road and Hillsboro Pike
Council District 25: Council Member Jeff Preptit
Project Status
Phase: Construction
Beginning Monday, August 26 the Hillsboro Pike entrance to Carrabba's Italian Grill will be closed until further notice. Nashville Electric Service (NES) completed the installation of five new utility poles September 2024.
Utility companies are still working to install their power/fiber lines on the new poles.
Project Timeline
Note: Estimated timeline dates are subject to change based on most current projected schedules from multiple vendors and departments.
Construction Schedule Milestones
- Advertisement for Construction: September 2023
- Contract Award: October 2023
- Contract Fully Executed: November 2023
- Estimated Construction Start: January 2024
- Estimated Construction Completion: Winter 2025
For more information, please contact the NDOT Project Manager at 615-862-8645.