Addition of left turn lanes at all four intersection approaches.
Project Funding: 100% Local
Project Limits
Intersection of Mt. View Road and Hamilton Church Road
Council District 8: Council Member Deonte Harrell
November 2023 Update
Phase: Right-of-Way (ROW) Acquisition
- Right-of-Way (ROW) acquisition underway
- Utility coordination underway
- Construction plans and final details in-progress
Project Timeline
Note: Estimated timeline dates are subject to change based on most current projected schedules from multiple vendors and departments.
Project Development Schedule Milestones
- Final Construction Plans: Quarter 1 2024
- Right-of-Way (ROW) Acquisition: Underway
- Utility Coordination: Underway
Construction Schedule Milestones
- Advertisement for Construction: Quarter 1 2024
- Contract Award: October Quarter 2 2024
- Contract Fully Executed: Quarter 2 2024
- Estimated Construction Start: Quarter 3 2024
- Estimated Construction Completion: Quarter 2 2025
For more information, please contact the NDOT Project Manager at 615-862-8645.