The Old Hickory Boulevard and Pettus Road Roundabout project will entail the design and construction of a new single lane mini roundabout for the intersection of Old Hickory Boulevard at Pettus Road. Improvements include the replacement of an existing two-way stop with a single lane modern mini roundabout including curb and gutter and restriping as needed. The roundabout will be constructed within the existing right-of-way and be mountable to allow for truck traffic.
Project Funding: 100% Local
Project Limits
Roundabout at Old Hickory Boulevard and Pettus Road – 0.13 miles
Council District 31 and 33: Council Member John Rutherford and Council Member Antoinette Lee
Project Update: May 2024
Phase: Conceptual Design
The design consultant has completed the preliminary design plans for the roundabout. The plans are currently under internal review.
Project Timeline
Note: Estimated timeline dates are subject to change based on most current projected schedules from multiple vendors and departments.
Project Development Schedule Milestones
- Consultant Selection: November/December 2023
- Preliminary Engineering: June 2024
- Environmental/ National Environmental Policy Act (NEPA): To be determined
- Design (Plans development): To be determined
- ROW Acquisition start (duration): To be determined
- Utility Coordination: To be determined
- Final Construction Plans: To be determined
Construction Schedule Milestones
- Advertisement for Construction: To be determined
- Contract Award: To be determined
- Contract Fully Executed: To be determined
- Estimated Construction Start: To be determined
- Estimated Construction Completion: To be determined
For more information, please contact the NDOT Project Manager at 615-862-8595.