Project Limits
Intersection of Estes Road and Hobbs Road: View the detour plan
Council District 34: Council Member Sandy Ewing
Project Information
This project will include addition of left turn lanes at all four intersection approaches, new sidewalks with curb and gutter and stormwater improvements.
- Estes Road at Hobbs Road Existing Conditions
- Estes Road at Hobbs Road Proposed Conditions
- Proposed Intersection Improvements Design Concept
Phase: Bidding and Pre-Construction
- Construction is expected to begin early summer
- ARAP permitting in-progress.
- Utility coordination is on-going with Metro Water Services, Piedmont Gas, Nashville Electric Service, AT&T, Comcast, and Google (fiber)
Community Engagement
Wednesday, November 6 at 3:30 p.m. NDOT staff held a meeting to discuss the proposed intersection improvements and detour plan for the project.
Project Timeline
Note: Estimated timeline dates are subject to change based on most current projected schedules from multiple vendors and departments.
Project Development Schedule Milestones
- Final Construction Plans: Completed January 2025
- Right-of-Way (ROW) Acquisition: Completed March 2025
- Utility Coordination: Underway
- Initial Utility Relocations (start): Underway
Construction Schedule Milestones
- Advertisement for Construction: To be determined
- Contract Award: To be determined
- Contract Fully Executed: To be determined
- Estimated Construction Start: To be determined
- Estimated Construction Completion: To be determined
For more information, please contact the NDOT Project Manager at 615-862-8645