James Avenue Sidewalk Project
The James Avenue Sidewalk Completion Project fills gaps in the sidewalk network and provides neighborhood connectivity to West Park, West Park Neighborhood Community Center, Charlotte Park, and across Briley Parkway. This project will be constructed on the southeast side of the street and includes new 5'-8' sidewalk and 4' furnishing zone along with curb, gutter, and storm drainage.
Funding Source for NEPA/Design/ROW: 100% Local
Funding Source for Construction: 80% Federal, 20% Local
Project Limits
Robertson Avenue to Morrow Road (0.50 miles)
Council District 20: Rollin Horton
Quarterly Update: November 2024
Phase: Consultant Selection
The Consultant Selection process was recently initiated. The Nashville Department of Transportation and Multimodal Infrastructure (NDOT) staff anticipates having a consultant onboarded by the end of the first quarter of 2025.
Project Timeline
Note: Estimated timeline dates are subject to change based on most current projected schedules from multiple vendors and departments.
Project Development Schedule Milestones
- Consultant Selection: April 2024
- Preliminary Engineering: April 2025
- Environmental/NEPA: April 2025
- Design (Plans development): January 2026
- ROW Acquisition start (duration TBD): Summer 2026
- Utility Coordination: Summer 2026
- Final Construction Plans: TBD
Construction Schedule Milestones
- Advertisement for Construction: TBD
- Contract Award: TBD
- Contract Fully Executed: TBD
- Estimated Construction Start: TBD
- Estimated Construction Completion: TBD
For more information, please contact the NDOT Project Manager at 615-862-8748.