Project Limits
Jefferson Street at 21st Avenue North and 28th Avenue North
Council District 21: Council Member Brandon Taylor
December 2023
Phase: Design
The Nashville Department of Transportation and Multimodal Infrastructure (NDOT) has begun preliminary Right-of-Way (ROW) plans design on the intersection improvements at 21st Avenue North and Jefferson Street. The design for the intersection of 28th Avenue North and Jefferson Street is pending further discussion with the community and stakeholders.
Jefferson St/28th Ave N Intersection Project Community Meeting: Thursday, December 14 at 6 p.m.
Next quarter: NDOT anticipates continuing preliminary right-of-way (ROW) plans design.
Additional Project Information
- 21st Avenue North Initial Design Concept (subject-to-change)
- 28th Avenue North Initial Design Concept (subject-to-change)
- Public Meeting Transcript- May 14, 2019
Project Description
This project will involve the design and construction of intersection improvements at 21st and 28th Avenues at Jefferson Street to improve the safety, mobility, and capacity of the intersections. The elements of the improvements may include right turn lanes, decorative pedestrian and traffic signals, improved crosswalks and striping and possibly the construction of a roundabout at 28th as an alternate design.
This project is federally funded, locally managed and is monitored by the TDOT Local Programs Development Office.
Project Funding: 80% Federal and 20% Local
- Length: 0 linear feet
- Cross-Section: 11-foot right turn and 5-foot sidewalk; 16-18-foot lanes for the roundabout.
- Estimated Project Cost: $3,900,000
Timeline
Note: Estimated timeline dates are subject-to-change based on most current projected schedules from multiple vendors and departments.
Project Development Schedule Milestones
- Consultant Selection: August 2018
- Preliminary Engineering: October 2023
- Environmental/NEPA: August 2013, re-evaluation to be determined
- Design (Plans development): On-hold
- ROW Acquisition start (duration): To be determined
- Utility Coordination: To be determined
- Final Construction Plans: To be determined
Construction Schedule Milestones
- Advertisement for Construction: To be determined
- Contract Award: To be determined
- Contract Fully Executed: To be determined
- Estimated Construction Start: To be determined
- Estimated Construction Completion: To be determined
For more information, please contact the project manager at 615-862-8730.
Jefferson Street Aerial View, 21st Avenue North
Jefferson Street Aerial View, 28th Avenue North