Project Limits
- Phase 1: Gallatin Road/Neelys Bend Road intersection to Madison Street
- Phase 2: Madison Street to Old Hickory Boulevard (S.R. 45)
Timeline
Note: Estimated timeline dates are subject to change based on most current projected schedules from multiple vendors and departments.
- Construction Plans: Completed June 2020
- Right-of-way Acquisition, Phase1: Completed 2021
- Right-of-way Acquisition: Phase 2: Completed
- Advertisement for Bids: August 16, 2020
- RFP opening bids October 27, 2020
- Groundbreaking: February 8, 2021
- Utility Relocations:
- Phase 1: January – August 2021
- Phase 2: Started April 2020
- Construction Start Date:
- Phase 1: April 2021
- Phase 2: February 2022
- Construction Duration: Anticipated 1.5 years (18 months)
- Construction Completion Date: September 2022
For more information, please contact the project manager at 615-862-8635.