This project will construct intersection improvements along Nolensville Pike at McNally Drive and Natchez Court that were identified in Envision Nolensville as critical to improving pedestrian access and safety along the growing corridor. Intersection improvements include sidewalks, Americans with Disabilities Act (ADA) upgrades (curb ramps, pedestrian lighting, etc.), curb and gutter, striping, transit stop improvements (relocations, shelters, boarding pad, etc.), pedestrian signals and drainage.
Project Limits
Nolensville Pike from McNally Drive to Natchez Court
Council Members: Courtney Johnston and Sandra Sepulveda
Project Update: May 2024
Phase: Environmental/National Environmental Policy Act (NEPA)
The Nashville Department of Transportation and Multimodal Infrastructure (NDOT) completed the National Environmental Policy Act (NEPA) documentation, and it was accepted by the Tennessee Department of Transportation (TDOT) at the beginning of May 2024. The department anticipates that the project will move into the plans development phase over the next few months.
Project Timeline
Note: Estimated timeline dates are subject to change based on most current projected schedules from multiple vendors and departments.
Project Development Schedule Milestones
- Consultant Selection: July 2021
- Preliminary Engineering: June 2023
- Environmental/NEPA: March 2024
- Design (Plans development): September 2024
- ROW Acquisition start (duration): Summer 2024 (anticipated 9-month duration)
- Utility Coordination: Summer 2024
- Final Construction Plans: Winter 2025
Construction Schedule Milestones
- Advertisement for Construction: To be determined
- Contract Award: To be determined
- Contract Fully Executed: To be determined
- Estimated Construction Start: 2025/2026
- Estimated Construction Completion: (To be added after receipt of construction schedule.)
For more information, please contact the NDOT Project Manager at 615-862-8748.